Amazon build to suit (BTS), Fulfilment Centre for phase one is located in Industrial City of Abu Dhabi (ICAD) which is a free zone dedicated to industrial processes. Spanning across 40 sq. km. ICAD is part of Musaffah, a popular industrial district located in the southwest of Abu Dhabi. The master development is one of the most important economic zones in the UAE housing several factories and a port.
Once soil has been improved and the plot leveled by another contractor, RAQ will begin the execution project for the Amazon fulfillment center. Client targeted time duration for the completion of “Build to Suit (BTS), Fulfilment Centre (FC) Phase 1 – “AUH1” project will be in 14 months (420 days).
The project has been directly commissioned by Amazon USA and is run with their standards.
As always, we plan our project in phases and divide areas in zones for easy deployment of resources.
Erection of steel starts of in Zone 2. We start the erection from the left; this is the absolution center of the entire building.
Madar at Al Jada is a unique set of buildings designed to house leisure and entertainment facilities for Arada’s vibrant upcoming residential and commercial community in Sharjah.
The project’s construction methodology entailed a hybrid approach, wherein both reinforced concrete (RCC) and steel structures were concurrently executed by two teams, enabling seamless progress.
The design of the facade was carefully executed to harmonize with the pre-existing sales center, while the construction of the facade incorporated GRC fins.
We have devised a bespoke construction methodology to facilitate the implementation of the building, taking into consideration the seamless integration of its structure and architectural design.